10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The EPE exam has 70 questions and runs 3 hours 30 minutes.
These 10 free EPE questions are organized by exam domain, so you can see how each part of the Electrical Plans Examiner blueprint is tested. Reveal the answer and explanation under each question.
Domain 2: Services
Question 1
A utility-supported short-circuit study gives 18 kA of available fault current at a new commercial service. The switchboard is marked 10 kA short-circuit current rating (SCCR); its main breaker has a 65 kA interrupting rating at the service voltage. No evaluated protective combination establishes a higher switchboard rating. The designer argues that the main breaker's rating resolves the issue. What is the decisive finding?
Show answer & explanation
Correct answer: A - The switchboard's 10 kA SCCR is inadequate even though the main breaker's interrupting rating is sufficient.
Question 2
A one-family dwelling qualifies for the optional service calculation in NEC 220.82 and will have a 120/240 V, three-wire service. Its eligible general-and-appliance load totals 42,000 VA before demand factors. Air conditioning is 8,000 VA. Five separately controlled electric space-heating units total 18,000 VA; controls prevent heating and cooling from operating together. There are no other loads. Using the 2023 NEC optional method, what is the smallest standard ampere rating for the service main circuit breaker that meets the calculated load?
Show answer & explanation
Correct answer: B - 150 A
Question 3
A new detached workshop is supplied by a 120/240 V feeder in PVC raceway. The one-line shows two ungrounded conductors and a neutral, but no equipment grounding conductor. At the workshop, the neutral is isolated from the enclosure, and the enclosure is connected to a local grounding electrode system with a documented resistance of 7 ohms. What essential part of the ground-fault return path is still missing?
Show answer & explanation
Correct answer: B - An equipment grounding conductor installed with the feeder back to its source.
Domain 3: Branch Circuit and Feeder Requirements
Question 4
On a new dwelling's 2023 NEC electrical plan, an individual 120 V, 20 A circuit supplies the refrigerator receptacle in the kitchen. The receptacle is 9 ft from the sink and does not serve a countertop. A combination-type AFCI breaker is specified, with no GFCI function. Which protection change is needed?
Show answer & explanation
Correct answer: A - Add Class A GFCI protection while retaining the required AFCI protection.
Question 5
A feeder protected by a 70 A circuit breaker serves a calculated 62 A noncontinuous load. Six current-carrying conductors share a raceway at 38 degrees C ambient. Copper THHN/THWN-2 conductors have 90-degree-C insulation, and all terminations are rated 75 degrees C. The applicable adjustment and correction factors are 0.80 and 0.91. Table 310.16 lists these 75-degree-C/90-degree-C ampacities: 8 AWG, 50/55 A; 6 AWG, 65/75 A; 4 AWG, 85/95 A; 3 AWG, 100/115 A. No other ampacity limitation applies. What is the smallest permitted phase-conductor size?
Show answer & explanation
Correct answer: C - 4 AWG copper
Domain 4: Wiring Methods and Distribution Systems
Question 6
The trench detail specifies an underground PVC raceway containing conductors marked THHN only. The designer states that solvent-welded joints will keep the raceway interior dry. Before accepting the conductor specification, the examiner should require which revision?
Show answer & explanation
Correct answer: D - Specify wet-location conductors, such as conductors marked THWN-2.
Domain 5: Equipment for General Use
Question 7
A listed packaged air conditioner is marked minimum circuit ampacity (MCA) 28 A and maximum circuit breaker 45 A. The proposed conductors have a final allowable ampacity of 30 A after all temperature and installation limits are applied. A 40 A breaker of the permitted type is specified. How should the examiner evaluate this conductor-and-breaker pairing?
Show answer & explanation
Correct answer: C - Accept the pairing; the conductor and breaker satisfy their separate nameplate limits.
Domain 6: Special Occupancies
Question 8
An area-classification report identifies an ignitible concentration of Group D vapor during normal processing. The lowest ignition temperature of the vapor mixture is 170 degrees C. All proposed switches meet the circuit voltage and ambient-temperature requirements. Which equipment marking matches both the location hazard and its temperature limit?
Show answer & explanation
Correct answer: B - Class I, Division 1, Group D; T3C, maximum surface temperature 160 degrees C.
Domain 7: Special Equipment
Question 9
The equipotential bonding detail for a permanent concrete swimming pool omits a metal handrail that extends into the water. The pump circuit already has Class A GFCI protection and an insulated equipment grounding conductor. Which correction addresses the risk of a voltage difference between the handrail and the surrounding pool structure?
Show answer & explanation
Correct answer: D - Connect the handrail to the pool's equipotential bonding system with 8 AWG solid copper.
Domain 8: Special Systems
Question 10
A commissioning report records two results after loss of normal power: required egress lighting classified under Article 700 is restored in 14 seconds, and a smoke-control load expressly classified under Article 701 is restored in 42 seconds. Both transfers are automatic, and no other source supplies either load during the interruption. Which timing finding belongs in the acceptance review?
Show answer & explanation
Correct answer: C - The egress-lighting transfer fails; the smoke-control transfer meets its time limit.